ORPOWER III GEOTHERMAL PROJECT POWER PLANT - NAIVASHA
Client: Ormat
This project is the construction of 35 Megawatt Geothermal Power Station at Naivasha in Kenya. The Power Station is located approximately 130 kms from Nairobi. It consisted of 3 steam collection pipes (36", 24" & 14") bringing steam to the plant and then one condensate re-injection pipe to return the condensate to the sub strata. The project includes all transport, from ships side, piping, mechanical installations, steel erection, turbine/generator alignments and QA/QC.
48 MEGAWATT POWER STATION REPAIR
Client: Westmont Power Kenya Limited
This turbine generator had thrown a blade thereby destroying the old rotor and severely damaging the housing. We then removed the damaged turbine rotor, and repaired the housing by welding. All welding procedures supervised by General Electric Company, the turbine manufacturer. We then replaced the new turbine into the repaired housing after receiving this from Canada. After boxing up the remainder of the machine; the turbine was restored to full service.